Some of the projects we have implemented:
- Reconstruction of the “Central” department store building in the city of Pryluky, Chernihiv region — 2006;
- Reconstruction of wastewater treatment facilities in the city of Pryluky, Chernihiv region, with an area of 630 sq.m — 2006;
- Construction of industrial and sewage pipelines with a pumping station and automation in the city of Pryluky, Chernihiv region, spanning 4 km — 2006;
- Construction of the “Praktyka” building materials supermarket in the city of Pryluky, Chernihiv region, with an area of 550 sq.m — 2007;
- Construction of monolithic foundations and concrete floors in a production facility in the city of Pyriatyn, covering 1,500 sq.m — 2007;
- Construction of a retaining wall in a shopping and entertainment complex in the city of Khmelnytskyi, 2 km in length — 2007;
- Capital repair of military town buildings No. 12, 14, 16, 17 in the city of Pryluky, Chernihiv region. Total area — 27,000 sq.m;
- Reconstruction of a building into an Agrotechnical College Institute in the city of Nizhyn, Chernihiv region — 2007–2008;
- Capital repair of livestock laboratory and calf barn at NAU NATI in the city of Nizhyn, Chernihiv region — 2007–2008;
- Construction of the “Kokteil” shopping and entertainment complex in Pryluky, Chernihiv region, with an area of 5,000 sq.m — 2007–2008;
- Construction of gas stations: 8 in Chernihiv region and 7 in Kyiv — 2007–2008;
- Construction of modular gas-filling stations in Chernihiv region — 2 stations;
- Construction of mobile communication antenna towers in Chernihiv region — 5 units;
- Installation of air conditioning and supply-exhaust ventilation systems at the tobacco factory PJSC “V.A.T. Pryluky” — 2008;
- Construction of a grain storage facility for 100,000 tons for LLC “Agro Elevator” in Ivkivtsi village, Pryluky district, Chernihiv region — 2009;
- Execution of construction and repair works at the tobacco factory PJSC “V.A.T. Pryluky” — 2009–2010;
- Construction of a complex for receiving, storing, and shipping grain and oilseeds “NIBULON” in Artemivka village, Chutove district, Poltava region, general contractor — 2010;
- Construction of a complex for receiving, storing, and shipping grain and oilseeds “NIBULON” in Maryanivka village, Hrebinka district, Poltava region, general contractor — 2010;
- Construction of a complex for receiving, storing, and shipping grain and oilseeds “NIBULON” in Romodan township, Myrhorod district, Poltava region, general contractor — 2009–2010;
- Construction of the “NIBULON” transshipment terminal for shipping grain and oilseeds via river in the city of Kremenchuk, Poltava region — 2010;
- Construction of the “NIBULON” transshipment terminal for shipping grain and oilseeds via river in Vitove village, Chyhyryn district, Cherkasy region — 2010;
- Construction of an elevator complex for receiving, storing, and shipping grain and oilseeds “NIBULON” in Denykhivka village, Tetiyiv district, Kyiv region, general contractor — 2011;
- Construction of transport infrastructure for grain cargo related to sea and river turnover at the “NIBULON” transshipment terminal in the city of Nova Odesa, Mykolaiv region — 2011;
- Construction of a grain storage facility for 100,000 tons at a feed mill in Kozelshchyna, Poltava region — 2011;
- Construction of the “HorodOk” entertainment complex, covering 3,000 sq.m, in Pryluky, Chernihiv region — 2011;
- Maintenance and repair of buildings and structures at the tobacco factory PJSC “V.A.T. Pryluky” — 2011–2012;
- Construction of the “NIBULON” elevator complex for receiving, storing, and shipping grain and oilseeds in Chyrske village, Pereiaslav-Khmelnytskyi district, Kyiv region, general contractor — 2012;
- Installation of concrete foundations totaling 908 cubic meters, KP “Kirovohradrembudmontazh” in Hlodosy village, Novoukrainka district, Kirovohrad region — 2012;
- Construction of a grain storage facility for 40,000 tons in Koziatyn, Vinnytsia region — 2012;
- Construction of an extension to the elevator at Nizhyn Grain Processing Plant in Nizhyn, Chernihiv region — 2012;
- Reconstruction of buildings into an elevator complex with a capacity of 94,000 tons for LLC “Hermes-Trading” in Svitlovodsk, Kirovohrad region — 2012;
- Construction of silo warehouses for grain storage with a capacity of 30,000 tons at PJSC “Pereiaslavsky EKHP” in Pereiaslavske village, Pereiaslav-Khmelnytskyi district, Kyiv region — 2012;
- Installation of concrete foundations totaling 3,000 cubic meters at the grain storage facility of LLC “Lanivtsi Invest” in Hrynky village, Lanivtsi district — 2012;
- Construction of a grain cleaning complex by LLC “Agrocentr Elevatorbud” in Savran township, Odesa region — 2012;
- Construction of a grain storage facility for 50,000 tons in the city of Pyriatyn, Poltava region — 2013;
- Construction of a grain warehouse at 66 Zavokzalna Street in the city of Pyriatyn, Poltava region — 2013;
- Construction of an elevator in Velyka Divytsia village, Obychivka village council, Chernihiv region, general contractor — 2013;
- Reconstruction of Pechanivka Grain Processing Plant in Pechanivka village, Romaniv district, Zhytomyr region — 2013;
- Construction of a grain processing and storage complex for 60,000 tons of grain for LLC “Signet-Center” in Andrushky village, Popilnia district, Zhytomyr region — 2013;
- Expansion of the feed workshop of LLC “Steikagro” in Hlanyshiv village, Pereiaslav-Khmelnytskyi district, Kyiv region — 2013;
- Construction of two silos of 12,000 tons each for grain storage at 35 Kotovskogo Street, Yagotin, Kyiv region — 2013;
- Construction of silos for grain storage at 11 Vokzalna Street, Berezan, Kyiv region — 2013;
- Construction of facilities for receiving, processing, storing, and shipping grain and oilseeds with a capacity of 120,000 tons at 7 Zaliznychna Street, Nyzy township, Sumy district, Sumy region;
- Construction of a grain processing and storage complex for 60,000 tons of grain in Andrushky village, Popilnia district, Zhytomyr region;
- Construction of grain storage facilities at the Yagotin branch of LLC “Baryshivska Grain Company” at 35 Kotovskogo Street, Yagotin, Kyiv region — Phase II;
- Construction of the “Agro-ERA” complex in Kyrylo-Hannivka village, Zinkiv district, Poltava region;
- Reconstruction of an enrichment plant into a feed plant with a capacity of 10 tons per hour for LLC “Avis-Ukraine” in Kosivshchyna village, Sumy district, Sumy region — 2014–2015;
- Reconstruction of buildings and installation of equipment for grain treatment at 350 Lenina Street, Berezan, Kyiv region — 2015;
- New construction of grain storage facilities for LLC “Baryshivska Grain Company” at 89 Pryluky Street, Nizhyn, Chernihiv region — 2015;
- Construction of reservoirs at Voronky station for LLC “Baryshivska Grain Company” in Voronky village, Chornukhy district, Poltava region — 2015;
- Administrative building for grain cleaning in Velyka Oleksandrivka village, Boryspil district, Kyiv region — 2015;
- Construction of an agricultural complex in Batiyevo village, Berehove district, Zakarpattia region — 2015;
- Reconstruction of buildings into a complex for receiving, cleaning, drying, storing, and shipping grain for LLC “Baryshivska Grain Company” at 55 Khmelnytskoho Street in Yarmolyntsi township, Yarmolyntsi district, Khmelnytskyi region — 2015;
- Installation of monolithic reinforced concrete foundations (FM 2 — 2 units, FM3 — 1 unit) during the construction of an elevator with a capacity of 12,400 tons of grain in Mykhailivka village, Holoborodky village council, Karlivka district, Poltava region;
- Construction of a filtration tank and fire reservoir from the floor storage warehouse of LLC “Vitchyzna”;
- Construction of a transport infrastructure facility “NIBULON” for transshipment of grain cargoes related to sea and river turnover at the transshipment terminal for shipping grain and oilseeds via river within the territory of Buzka village council, Voznesensk district, Mykolaiv region;
- Reconstruction of non-residential agricultural buildings into a complex for breeding, raising, and fattening pigs with auxiliary buildings and engineering networks in Haishyn village, Pereiaslav-Khmelnytskyi district, Kyiv region at 1/1 Shevchenka Street (prefabricated monolithic reinforced concrete construction of buildings No. 5–10);
- Construction of facilities for receiving and shipping grain and oilseeds to rail and road transport “NIBULON” at 17 Novo-Starobilskaya Street, Svatove, Luhansk region;
- Construction of silo trestles and galleries with a capacity of 5,500 tons at the “NIBULON” transshipment terminal in Bilenke village, Zaporizhzhia region, at 7 Shkilna Street;
- Installation of monolithic reinforced concrete foundations during the construction of silos with a capacity of 12,400 tons of grain in Mykhailivka village, Holoborodky village council, Karlivka district, Poltava region;
- Reconstruction of the grain elevator building with the installation of silos with a capacity of 20,000 tons for LLC “Vitchyzna” at 7/1, 7/2 Baturskyi Shliakh Street, Pytomnyk village, Konotop district, Sumy region.
Gallery
Bonfanti dryer running on sunflower pellets (biofuel)
Italian-made “PICCINI” plant